Phase 1 - Excavating / Concrete Work    Phase 2 - Framing   Phase 3 - Closing In

Phase 3 - Closing In



On June 11, 2005, Mike and Bobby installed 17 roof trusses (no crane).
On July 6, Mike and Daren on the roof and Bobby and Jacob on the ground installed the roof sheathing after
work until 10:30 pm. What dedication!




Ok, maybe Jacob did more
joking than helping!
Construction has really slowed down!
From August-September, the roofing, siding, and entry door were installed.
Here's a look at the inside looking from the garage door opening.



Here's some rainy day pictures of the outside.




Here's some more pictures of the inside. It's already becoming a messy garage!




In October, Bobby and Mike ran power from the house to the new 200 amp panel in the garage.



A trench was needed to bury the power, 2 Cat-5 lines, and RG-6 cables.
You never know what you might need in the future.

More to come...